Optimization of manual
work stations

The project

CUSTOMER
Industrial customer with >100 mio. € turnover p.a.

CHALLENGE
Manual work station within an automatic assembly line have significantly influenced the line cycle time and the customer requirement was not fulfilled.

PROJECT DURATION
12 month

RESULT
By re-structuring of the work content of each single work station, the manual assembly station was implemented without any negative effect into the automatic line. The customer requirement is fulfilled.

METHODS
MTM Analysis
Work Place Design
Promotex-Process Flow Analysis

Work stations